Monthly Reporting Requirements

In line with the PGO Finance Reporting Cycle, all reporting updates must be completed by working day 10. These updates include -

  • Status Update
  • Financial Update (including forecasting)
  • Schedule Update

The Project Governance Office and your PMO/Portfolio Manager (if applicable) will advise of upcoming deadlines.

Reporting Month Deadline (Snapshot Date)
December* 24 January 2022
January 14 February 2022
February 14 March 2022
March 14 April 2022
April 13 May 2022
May 14 June 2022
June 14 July 2022
July 12 August 2022
August 14 September 2022
September 14 October 2022
October 14 November 2022
November 14 December 2022

*Reporting deadline may differ from 10th working day due to public holiday/s and/or internal University processing times.

The information entered into these records forms the reports available in the Digital Project Reporting Dashboard.

Top of page

Digital Project Reporting Dashboard

The Project Governance Office has developed a Digital Project Reporting Dashboard to provide visibility of UQ's Project Portfolio within the scope of the PGMF. Please contact the Project Governance Office for any reporting requests.

Access the UQ Project Portfolio Overview (UQ staff login required).

Top of page

Project Performance Monitoring Criteria and Tolerances

The Project Performance Monitoring Criteria and Tolerances matrix defines project tolerance thresholds and performance indicators for use in completing status reporting and determining project health.

Access the Project Performance Monitoring Criteria and Tolerances (PDF, 125KB). Staff login required. 